CONSTRUCTION NOTICE: LIFT STATION IMPROVEMENTS
PROJECT DESCRIPTION
Decommissioning of existing lift stations & installation of new sanitary lift stations.
PROJECT DATES
Construction will commence at the end of June, and conclude at the end of October, 2023. Temporary road closures will be necessary to complete the work.
Approximate construction dates and locations are as follows:
CONSTRUCTION
July 6 – Aug 23 Dogwood St. 9th Ave to 13th Ave.
Sept 5 – 18 Dogwood St. between 14th & 17th Ave.
Sept 18 – Oct 6 13th Avenue
TBA Community Garden access road
SANITARY TIE INS
Oct 18,19 Ash St. & Community Garden Access Rd
Oct 18, 19 13th Ave & Ash St.
Oct 23, 24 Cedar St. and 17th Ave.
Oct 24, 25 Ash Street & 9th Ave.
Oct 24, 25 Dogwood & 9th Ave.
Oct 25, 26 Dogwood & 17th Ave.
*Please note that construction locations/dates are tentative. Further details regarding temporary road closures will be provided as they become available.
Please call the Village Office at 250-566-4435 with any questions or concerns.
Ash Street Lane Closure with TCPs Single lane alternating TMP