Order of Inspections
blank
Building Construction of Alteration Schedule
Inspections must be completed at varying stages during the project. A typical inspection schedule is as follows:
Inspection |
When to Inspect |
1. Footings |
When footing forms are complete, prior to pouring concrete. |
2. Foundation |
When foundation wall forms are complete, prior to pouring. If required, submit registered professional’s letters of assurance prior to framing. |
3. Backfill |
When the perimeter drain rock, drain tiles, foundation insulation (if applicable) and damp proofing is completed, prior to backfilling. The survey (if required) for the foundation location is required prior to approval of Backfill. |
4. Rough-in Plumbing |
When rough-in plumbing is completed prior to covering. Water or air test must be visually confirmed by Building Official. This can be completed in two inspections; Plumbing under the slab and above ground. |
5. Municipal Service Connection |
When sewer, water and storm lines are installed and connected to the municipal system, prior to backfilling or covering. |
6. Soil Gas |
After the soil gas control is installed |
7. Pre-slab |
Prior to pouring concrete floor slab. Air barrier system and insulation must be installed where applicable. |
8. Framing |
When framing, exterior sheathing, fire stopping, bracing, plumbing, HVAC and electrical are completed and prior to any interior and exterior finish being applied. The Village of Valemount – reviewed/stamped drawings, truss/beam details and mechanical ventilation checklist must be on site. |
9. Masonry Fireplace |
When masonry fireplace is constructed to the smoke chamber and again when the chimney is complete prior to interior or exterior finish. |
10. Chimney |
When the chimney is installed prior to interior or exterior finish. |
11. Insulation |
When insulation and vapour barrier are completed, prior to installing drywall or other finish. |
12. Solid Fuel Burning Appliance |
When the solid fuel burning appliance is installed but prior to covering up. |
13. Occupancy |
When building has received all applicable inspections and meets all health and safety requirements. If registered professionals letters of assurance are required, no occupancy will be granted until the letters of assurance have been received. If applicable, final sewage approval from Northern Health Authority is required prior to occupancy. |
14. Final |
When building is completed. |
Manufactured Home Inspection Schedule
Inspection |
When to Inspect |
Footing Foundation |
When excavation is complete, prior to pouring concrete. |
Occupancy Final |
When the following are complete:
|